HUD has opened a fast track for affordable rental construction. Mortgagee Letter 2026-13 creates the LIHTC Express Lane for FHA-insured Section 221(d)(4) new construction loans, giving experienced tax credit developers lighter processing, higher leverage and access for larger projects. Issued on 2 November 2026 and effective immediately, the letter is one of the most practical federal housing finance changes this year for developers and investors in workforce housing.
| At a glance | |
|---|---|
| Name / number | Mortgagee Letter 2026-13, Implementation of the LIHTC Express Lane Initiative for Multifamily Section 221(d)(4) New Construction Loans |
| Issuing body | U.S. Department of Housing and Urban Development (HUD), Federal Housing Administration |
| Issued | 2 November 2026 |
| Effective | Immediately; no sunset date |
| Scope | Section 221(d)(4) new construction with LIHTC-restricted rents; experienced sponsors and teams only |
Key changes under the LIHTC Express Lane
- No unit cap. The earlier limit of fewer than 200 units is removed, along with any loan size limit.
- 4% deals now eligible. Projects using 4% credits with tax-exempt bonds join 9% credit deals, which remain eligible.
- Higher leverage. The loan-to-cost limit rises from the earlier 65%–75% range to the standard 80%.
- Developer fee relief. The requirement to defer 25% of the developer fee is dropped.
- Later document deadlines. Final plans, specifications and third-party architectural and engineering reports are due at least 15 days before closing instead of before firm commitment.
- Lighter reviews. HUD keeps a 30-day target for firm commitment decisions, gives Express Lane deals priority concept meetings, and skips the separate appraisal division review unless a regional director asks for it.
Tax credit equity paid in at initial endorsement is capped at 10%. Standard underwriting under HUD’s MAP Guide, including debt service coverage and loan sizing, still applies.
Who is affected
The fast track is for proven teams. Sponsors must have developed, placed in service and stabilized at least three LIHTC deals in the past five years, and must show $1 million in liquidity and $5 million in net worth without third-party guarantors. Their stabilized LIHTC portfolio should run above 1.15 debt service coverage and 93% occupancy.
The rest of the team faces thresholds too. General contractors need five completed 221(d)(4) or LIHTC projects and five Davis-Bacon projects in the past ten years. Architects need five 221(d)(4) projects, and management agents must currently operate at least five LIHTC-compliant properties. Projects with project-based Section 8 assistance are excluded, as are sites with noise above 75 dB or unremediated contamination. Those deals can still use standard processing.
Timeline
- 13 March 2026: Executive Order 14394 on removing regulatory barriers to affordable home construction, cited by HUD as the basis for the change.
- 2 November 2026: HUD issues Mortgagee Letter 2026-13, effective immediately.
- Ongoing: The existing 2019 LIHTC pilot remains in place for other deal types.
Impact on the industry and investors
For developers, raising FHA loan-to-cost to 80% can reduce the equity gap that often stalls tax credit projects. Removing the unit cap opens the program to large urban deals, and adding 4% bond deals widens the pool of eligible projects. Later deadlines for final plans mean sponsors can lock in a commitment sooner and finish design work in parallel.
For tax credit investors and syndicators, the 10% cap on equity pay-in at initial endorsement and the high sponsor bar support credit quality. For lenders, the template-driven process should mean faster, more predictable execution.
The challenges are real. The experience and balance sheet tests exclude smaller and newer sponsors, and environmental consultations must start before the firm application, which front-loads work. HUD also has not published production targets, so the volume impact is unknown. The change sits alongside other recent federal moves to spur supply, such as the new Opportunity Zone designations, while rules like the HUD Section 214 final rule continue to shape the operating side of assisted housing.
Compliance: what to watch
- Check every team member against the eligibility tests before a concept meeting; one weak link can push a deal back to standard processing.
- Start Section 106 historic review, tribal consultation, floodplain notices and endangered species consultation early, as the letter requires them before the firm application.
- Prepare a binding tax credit investor funding agreement and, for 4% deals, the bond certification.
- Have a stabilization plan ready for any stressed deal in the sponsor’s existing portfolio.
FAQ
What is the HUD LIHTC Express Lane?
It is a streamlined FHA processing track, created by Mortgagee Letter 2026-13, for Section 221(d)(4) new construction loans on tax credit projects led by highly experienced teams.
Are 4% LIHTC deals eligible?
Yes. Deals using 4% credits with tax-exempt bonds are now eligible, alongside 9% credit deals.
Does the Express Lane change underwriting standards?
Standard MAP Guide underwriting still applies, but loan-to-cost rises to 80% and the 25% developer fee deferral requirement is removed.